• Description of the basics for injection against rising damp

    Two different CAPILASIL® products for injection as well as for facade protection.
    1. Solvent phase :
    BEAL formulates CAPILASIL® in a solvent phase based on a concentration of active ingredients composed of oligomeric siloxanes (10% concentration) by means of a high quality and high performance, de-aromatised solvent.
    Aromatics are largely eliminated, but some remain.
    The solvent is heavy to allow diffusion to continue after injection. Then the solvent will evaporate and give way to the barrier created by the polymerisation of the oligomeric siloxane system.
    The solvent is the transport agent of the product. It is non-polar so it does not mix with water. Initially, the solvent acts as a barrier and as soon as it evaporates, polymerisation takes place to form the real barrier (the barrier is effective on the day of injection). Any moisture present in the substrate is a factor which accelerates polymerisation.
    Do not use this “solvent” base if solvent-sensitive elements are present in the walls, on the floor and underneath the screed or concrete, etc. In this case, use CAPILASIL HEH2O (water-based).

    Heat (in cold periods) and ventilate the treated areas to evacuate evaporated solvents and humidity still present in the walls. The last aromatics still present in the products are naturally more odorous when heated. Storage heaters will therefore significantly increase the smell of the remaining aromatics (e.g. a cold sauce when heated will release its aromatics).

    The drying time depends on the components of the wall coverings (paint, plaster, lime, cement, tiles, etc.), heating (cold periods) and ventilation. It therefore depends on the inhabitant of the premises.
    In general, for uncovered walls, it takes from 6 months to a year and a half, or even longer. In the early stages of construction sites open to the wind (frames not placed), there was a rapid drying out period of around 2 and a half to three months.

    2. Aqueous phase:
    BEAL formulates CAPILASIL® HEH20 based on siloxanes diluted in water.
    The advantage of this type of product is that it is completely odourless.
    On the other hand, it should be noted that the injection will bring into the substrate a significant quantity of water necessary for the diffusion of the siloxanes. This water will also have to evaporate. Drying process will therefore be much longer than with a solvent-based product whose solvent evaporates more easily. There will also be a formation of additional salts since water is added in large quantities in an alkaline medium.

    The barrier is not effective on the day of injection, but much later. Siloxanes start to polymerise as the water evaporates, therefore slowly. Polymerisation usually begins after one month and more quickly in periods of high heat.
    There is also the risk that in the presence of increased rising damp, the barrier will rise and be diluted before polymerisation has taken place.

    The polymerised siloxanes will then be effective after all the water in the products and walls has evaporated. Drying time depends on the components of the wall coverings (paint, plaster, lime, cement, tiles, etc.), heating (cold periods) and ventilation. It therefore depends on the inhabitant of the premises.
    In general, for walls that are not covered, it takes from 6 months to two years.

    On sites open to the wind (unplaced frames), much faster drying out has been observed. After 10 months, convincing results were observed.

Cookies.

Beal International installs cookies to analyse the use of its website, to improve your browsing experience and to better tailor the content and the advertisements on its website to your interests. Partners with whom Beal International collaborates can also install advertising cookies via the Beal International website in order to show you advertisements that may be relevant to you on other websites and social media. Click on "I accept all cookies" to accept the cookies and go directly to the website or click on “Change settings” to change your cookie preferences. Please note that if you block certain cookies, this may hinder the correct functioning of the website.

Change settings I accept all cookies
Edit Cookies.
  • Some cookies are essential for the functioning of the site and are automatically active (eg session ID) You can’t disable these cookies. Beal International’ first party analytical cookies make it possible to analyse traffic on Beal International website. These cookies are purely statistical. They enable Beal International to analyse the use of its website by, for example, quantifying visits to the site, determining whether there are perfomance issues or bottlenecks, etc. This information helps us to provide the best service and performance.

  • We use Google Analytics to study the browsing behaviour of visitors to this site. This is a website analytics service provided by Google Inc. Google Analytics collects information on an anonymous basis, such as the number of visitors to this site, their country, region and city of origin, the type of browser and operating system they are using, the date, time and duration of visits, the pages consulted, and what other websites they visited prior to coming to this site. Our use of Google Analytics includes the Demographics and Interest Reporting component.

  • These cookies may be set through this site by our advertising partners. They may be used by those companies to build a profile of your interests and show you relevant adverts on other sites. They do not store directly personal information, but are based on uniquely identifying your browser and internet device. If you do not allow these cookies, you will experience less targeted advertising.

Save